Ethiopia completes its portion of the Ethio-Kenya power line: EEP

ADDIS ABABA– The construction of the 433 km of Ethio-Kenya power transmission line is completed fully while the substation has reached 88 per cent and expected to complete up to November 2019, Ethiopian Electric Power (EEP) said.

The Ethiopia-Kenya interconnector high voltage electric highway is a joint project of the two countries which covers 1055 km with a capacity of

carrying up to 2,000 megawatts. Some 433 km of the total lies in Ethiopian border.

EEP Communication Director, Moges Mekonnen told The Ethiopian Herald that the construction of the 433 Km of the highway that lies in Ethiopia is fully completed and waiting for the completion of construction of a substation.

Moges stated that the construction of the substation in Wolayta-Sodo town has reached 88 per cent and is planned to be finalized by November 2019.

The director reiterated that as the construction of the power transmission line is completed fully, a completion certificate was provided to the contractor and the line waits for the end of the converser station for a power test.

According to him following the completion of the remaining 12 per cent of the substation construction, the testing and conversion will be held within five months. Adding that the project is in a good prospect and making the powered highway ready for power transmission will be finalized up to April 2020.

Meanwhile, Moges stated that following the completion of the necessary preconditions, the power transmission will start based on the agreement of the two countries.

According to him, the government of Ethiopia has spent about 333 million dollars for the construction of the transmission line and the substation.

Moges also noted that this power highway project has the capacity of interconnecting East African countries with electricity as the highway is constructed with the capacity of carrying up to 2,000 MW. He said that there is a possibility to transmit the power to Tanzania, Uganda and other countries in the long run after Ethiopia completes its power generating megaprojects.

The 1055 km long joint project which aimed at achieving regional power interconnection in East Africa was launched in 2013 with the total budget of USD1.26 billion.

The Ethiopian Herald August 10, 2019

 BY DARGIE KAHSAY

Recommended For You

Leave a Reply

Your email address will not be published. Required fields are marked *